BOSTON—Acadia Center is calling for a public review and full transparency following yesterday’s announcement that Northern Pass Transmission’s hydro-only bid, a partnership between Eversource and Hydro Quebec, was selected as the sole winner of the Massachusetts Clean Energy RFP.

The RFP, called for by a 2016 energy law, sought clean energy for about 17% of Massachusetts’ annual electricity needs.  Although more than 40 bids were submitted in the summer of 2017—including several with a blend of on-shore wind and hydroelectricity, the Department of Energy Resources (DOER) and a group of Massachusetts utilities, which included Eversource, chose one controversial project, owned in large part by a subsidiary of Eversource. As the winning bid, Eversource and Hydro-Quebec will begin the process of negotiating long-term, multi-billion-dollar contracts with Eversource, National Grid and Unitil, the other distribution companies.

“Acadia Center is disappointed but not surprised that the process has resulted in the recommendation of the Northern Pass project,” said Daniel Sosland, president of Acadia Center. “Acadia Center has long asserted that clean energy bids should include the region’s wind resources and not only hydropower imports and has further been concerned that having utilities review bids in which they have a financial interest creates a clear conflict of interest that undermines public confidence in the process.”

Acadia Center supported the 2016 energy law and the Commonwealth’s pursuing a large-scale procurement of clean energy, particularly arguing for environmental protections, a preference for a blend of new renewables and hydro, and guaranteed winter energy delivery to control price spikes, all of which the statute and RFP specified. One provision that Acadia Center argued against—but was still allowed in the 2016 energy law—was allowing the utilities to bid for the contract and serve on the selection committee.

“Under the terms of the RFP, the selected project was to provide the greatest benefit with limited risk to Massachusetts ratepayers.  We don’t know the relative benefit-cost ratios because the price terms are confidential, but choosing only one project from an existing importer of electricity has major risks,” said Amy Boyd, Senior Attorney at Acadia Center. “Hydro-Quebec has previously curtailed power to New England in winter months, when demand in Quebec is highest. Similarly, reliance on a single project has its own risks. Northern Pass Transmission faces serious opposition due to its land use impacts and its projected in-service date has been delayed previously.”

After the contract is negotiated it will be reviewed by the Department of Public Utilities (DPU), and the review must include a report from an independent evaluator and the participation of the Attorney General’s office. Under the statute, Eversource is also eligible for an additional incentive of up to 2.75% of the contract price for its share of the energy, as one of the contracting distribution companies. The public must be privy to any evaluation of the fairness of this and other aspects of the contract.

“Acadia Center believes that a full public report from the statutorily required independent evaluator and scrutiny by the Attorney General are important next steps. The public needs to have full confidence that this was a fair process and the benefits of other bidders were evaluated reasonably. The current ongoing procurements for offshore wind and future procurements are even more crucial to progress towards a clean energy future,” said Mark LeBel, Staff Attorney for Acadia Center. “If this contract is approved, the DPU should deny Eversource an additional incentive as a distribution company. Ratepayers don’t need to give Eversource additional money as a backstop for a contract where they are also on the other side.”


Media Contacts:

Amy Boyd, Senior Attorney
aboyd@acadiacenter.org, 617-742-0054 x102

Mark LeBel, Staff Attorney
mlebel@acadiacenter.org, 617-742-0054 x104

Krysia Wazny, Communications Director
kwazny@acadiacenter.org, 617-742-0054 x107