National Grid can also collect on a performance incentive of $750,000 if 75 percent of the target number of chargers are successfully installed, and $1.2 million for 125 percent of the target. That feature drew criticism from groups including the state attorney general and the Acadia Center, which said the bonuses should be tied to metrics like increased electric vehicle adoption, emissions reductions and reduced costs.

Massachusetts is aiming to get 300,000 zero-emission vehicles on the road by 2025, and the number of EV chargers has been ticking steadily upward. As of a year ago, 1,158 Level 2 ports and 128 fast chargers were available, according to the DPU, compared to 963 Level 2 ports and 83 fast chargers in the prior year.